燃油燃氣鍋爐從安裝前期的施工準備一直到工程驗收任何階段都有需要注意的問題,都需要按照步驟一步步的來完成。下麵小編給大家總結了一些燃油燃氣鍋爐的安裝要求,一起看一下。
From the construction preparation in the early stage of installation to the project acceptance, there are problems that need to be paid attention to in any stage, which need to be completed step by step. The following is a summary of the installation requirements of some oil and gas boilers. Let's have a look.
(1)鍋爐在安裝施工前,依據規程先辦理鍋爐安裝審批手續,待質量技術監督局審批後,施工隊做好施工準備。
(1) Before boiler installation and construction, the boiler installation approval procedures shall be handled according to the regulations. After the approval of quality and Technical Supervision Bureau, the construction team shall make good construction preparation.
(2)組織施工人員學習,熟悉鍋爐圖紙與鍋爐安裝有關方麵的技術資料,規範、規程後方可進行施工
(2) Organize the construction personnel to study, be familiar with the boiler drawings and technical data related to boiler installation, and carry out the construction only after the specifications and procedures
(3)鍋爐在水平運輸時,要使枕木高於鍋爐基礎,保證基礎不受損壞。
(3) When the boiler is transported horizontally, the sleeper shall be higher than the boiler foundation to ensure that the foundation will not be damaged.
(4)燃燒器管路安裝:燃燒器自身的燃油管路已接好,且留有進,回油兩個燃油軟管接口,安裝時隻需將供,回油管接上即可。
(4) Burner pipeline installation: the fuel pipeline of the burner itself has been connected, and there are two fuel hose interfaces for oil inlet and return. When installing, just connect the oil supply and return pipes.
(5)控製櫃安裝:控製箱上匯集了燃燒器的開關按扭,燃燒器的程序控製器以及自動操作和保護裝置的接線端,其控製線已接好,用戶隻需接通外來總電源。
(5) Installation of control cabinet: the switch button of burner, the program controller of burner and the terminal of automatic operation and protection device are assembled on the control box. The control line has been connected, and the user only needs to connect the external main power supply.
(6)水泵安裝:將水泵抬到基礎上就位後,用墊鐵墊平找正,然後用混凝土將地腳螺栓灌注好,待混凝土強度達到75%時,再複查水泵不平度,緊好地腳螺栓。
(6) Water pump installation: after the water pump is lifted to the foundation and put in place, it shall be leveled and aligned with pad iron, and then the anchor bolts shall be poured with concrete. When the concrete strength reaches 75%, the unevenness of the water pump shall be rechecked and the anchor bolts shall be tightened.
(7)煙囪、壓力表、水位表等等問題,都是需要在安裝時嚴格按照鍋爐廠家的安裝要求行事。
(7) Chimney, pressure gauge, water level gauge and other issues, are required to be installed in strict accordance with the boiler manufacturer's installation requirements.
所有的工作或者要求都是為了施工順利的完成,大家一定要根據要求來做。
All the work or requirements are for the smooth completion of the construction, we must do according to the requirements.